• Concrete is poured to form pile caps on the west side of the building’s footprint.
    Concrete is poured to form pile caps on the west side of the building’s footprint.
  • Columns poured by the west side of the building’s footprint.

    Columns poured by the west side of the building’s footprint.

  • Piles formed at the south side of the Tower along 6th Street.

    Piles formed at the south side of the Tower along 6th Street.

     

  • In late January, the cranes were installed and work on the foundations was started
    In late January, the cranes were installed and work on the foundations was started.
  • December 2013
    ​Tower is over half way to top out and is shown towering over the existing Courthouse located to the left. The 110 Tower is show at the top right.
  • January 2013
    ​Preparing the site for preliminary foundation work.
  • February 2013
    ​Aerial shot of the installation of concrete auger cast piles.
  • The 16th floor concrete slab is complete and the 17th floor is underway.
    ​The 16th floor concrete slab is complete and the 17th floor is underway. The tower crane pictured on the left side of the building is at its max height of approximately 400 feet.
  • A view looking down from the atrium on the top floor of the main lobby.
    ​A view looking down from the atrium on the top floor of the main lobby.
  • A view looking up to the top of the atrium in the main lobby
    A view looking up to the top of the atrium in the main lobby.